Carnation Solar News
Go here to show your opposition to the project - submit a comment to the OPSB
The Carnation Application has been filed with the OPSB
Go here to show your opposition to the project - submit a comment to the OPSB
The developer, National Grid Renewables (NGR) - now known as Geronimo Power, for the Carnation Solar project located in Amanda Township, has begun the formal application process with the Ohio Power Siting Board (OPSB). Below is a timeline information regarding the project:
06/10/2025 - The OPSB issued the timeline for the staff report due date, public hearing, and evidentiary hearing:
07/25/2025 - Staff report due on or before this date
08/11/2025 - Public Hearing to be held at the Amanda Clearcreek High School - 5pm
09/09/2025 - Evidentiary Hearing to be held at the Public Utilities Commission of Ohio hearing room, 180 East Broad St, Columbus, Ohio
06/02/2025 - Aundrea Cordle appointed Ad Hoc member on behalf of the Fairfield County Board of Commissioners
05/30/2025 - National Grid Renewables rebranded as Geronimo Power. National Grid Renewables was previously divested from the parent company National Grid and acquired by Brookfield Asset Management
05/27/2025 - Dave Wilcox appointed Ad Hoc member on behalf of Amanda Township
05/15/2025 - The application fee was paid by the project developer and around 05/14/2025 the application was served to the required recipients (county commissioners, district library, township trustees, soil and water conservation district, and regional planning commission)
05/07/2025 - The application was found to contain sufficient information to begin application review
04/07/2025 - The OPSB staff were supposed to render a decision on completeness of the Carnation Solar project application by 04/08/2025. On 04/03/2025 the developer submitted a motion to extend the date of completeness to May 7th, the motion was granted. So, the decision on the application being complete will now be determined on or before May 7th. Note, once the application is deemed complete and a letter of completeness is issued by the OPSB the county commissioners and township trustees have 30 days to chose their Ad Hoc board members.
02/07/2025 - The OPSB application for the Carnation Solar project was filed -- You can view the OPSB case documents (application, legal briefs, public comments, etc.) for Carnation Solar by clicking here.
10/10/2024 & 11/20/2024 - The two required developer information meetings held for the Carnation Solar project (October 10, 2024 from 5-7pm at the Amanda Clearcreek High School cafeteria and Nov. 20 from 5-7pm and the Amanda Primary School) -- THANK YOU for your attendance!
09/18/2024 - developer filed pre-application letter with the OPSB. This kicks off the official OPSB process.
Part of the Staff Investigation is review of the public comments submitted to the OPSB regarding the project. Your comment of opposition is needed.
NOW IS THE TIME TO SUBMIT COMMENTS TO THE OPSB DIRECTLY - THIS PAGE WILL ASSIST YOU IN SUBMITTING A COMMENT!
To receive updates via email from Protect Amanda Township submit your contact information here .
Note, there is a difference between the comments submitted to the OPSB and those submitted at the developer information meetings. Since the information meetings have been completed please submit a comment to the OPSB and at the public hearings once they are scheduled - stay tuned.
Click Here to Join Protect Amanda Township Inc. Membership
*Please: Become a member of Protect Amanda Township Inc.
Membership in the organization means that you are an adult that supports the mission of Protect Amanda Township Inc.
Membership does not have any financial obligations, it just states that you are in support of PAT.
Membership will allow PAT to quantify the people who have said to us that Carnation Solar does not belong in Amanda Township.
IF everyone that has said to us that they are against this project becomes a member of PAT there will be a clear message that our community deserves better than industrial solar.
Membership is simple. Just complete a google form with your information and your electronic signature showing your support of PAT and their mission.
Share this information with your family, friends, co-workers and everyone to let them know that we need their support.
PLEASE click the link above to fill out a membership.
Have every adult in your household fill out the form.
Share this link with everyone who supports us.
The PAT group has retained the most experienced attorney regarding intervenors for solar projects before the OPSB to represent us. We need legal representation for the OPSB process, which is a formal legal process. We have now formed a corporation, Protect Amanda Township Inc., and can formally accept contributions.
You can send your contributions to:
Protect Amanda Township, Inc.
PO Box 46
Amanda, OH 43102
Make checks payable to: Protect Amanda Township, Inc.
If you would like to drop off a donation or have one picked up just let us know. You can email us at: protectamandatownship@gmail.com.
Please submit an official comment opposing the Carnation Project, this page will assist you. If you use a different method please be sure to include the project case number 24-0881-EL-BGN in your correspondence with the OPSB since that is how they match up comments with a specific project.
*Note: Please fill out our contact form found here. This will allow us to keep you informed of the solar project in Amanda Township (aka Carnation Solar) and things you can do to oppose the project. Thank You!